基于BIM的碾压混凝土坝施工进度-成本联合管控
作者:
中图分类号:

TV51;TV642.2

基金项目:

国家自然科学基金(51879147)


Construction schedule-cost joint control of RCC dams based on BIM
Author:
  • 摘要
  • | |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 文章评论
    摘要:

    为解决施工进度与成本联动性不强,施工过程中缺乏对进度及成本的有效监控,难以及时发现偏差并调整实施计划等问题,将建筑信息模型(BIM)和改进挣值法应用于碾压混凝土坝施工进度-成本联合管控中。通过建立大坝三维模型,用Primavera 6.0软件编制进度计划,计算施工成本,再将进度、成本信息导入Navisworks软件,实现大坝三维模型与进度-成本信息的匹配关联,构建基于BIM的大坝施工期5D进度-成本可视化模型及动态联合管控信息平台。利用平台API接口和C#.NET语言二次开发插件实现大坝施工进度-成本的仿真模拟和任意时刻施工面貌及浇筑单元的进度、成本、资源配置和浇筑强度等信息可视化查询;监测建造过程中改进挣值指标的动态变化并预警,及时调整实施计划实现施工过程进度-成本联合管控。工程应用验证了基于BIM的碾压混凝土坝施工进度-成本联合管控技术的实用性和优越性,具有推广价值。

    Abstract:

    In order to solve the problems such as weak linkage between construction schedule and cost, lack of effective monitoring on schedule and cost during construction, difficult to find the deviation and adjust construction plans in time, this paper introduced a method which applies BIM technology and improved earned value method to construction schedule-cost joint control of RCC dams. By establishing a 3D model of the dam, using Primavera 6. 0 software to prepare a construction schedule and calculate the construction costs, and importing construction schedule and cost information into Navisworks software, the relevance matching of the 3D model and the schedule-cost information was realized. Also a 5D construction schedule-cost information visualization model and a dynamic joint management platform based on BIM during construction period was established. Secondary development plug-ins based on C#. NET and API interface can realize analogue simulation of the schedule-cost and visual information query at any time such as construction appearance and schedule, cost, resourceallocation, pouring strength of the placing unit. Monitoring the dynamic changes of improved earned value indicators, early warning during construction and adjusting construction plans can realize schedule-cost joint control during the construction. The engineering application verifies the practicability and superiority of the technology, which possesses the value of popularization.

    参考文献
    相似文献
    引证文献
引用本文

黄建文,毛宇辰,王东,等.基于BIM的碾压混凝土坝施工进度-成本联合管控[J].水利水电科技进展,2019,39(5):66-72.(HUANG Jianwen, Mao Yuchen, WANG Dong, et al. Construction schedule-cost joint control of RCC dams based on BIM[J]. Advances in Science and Technology of Water Resources,2019,39(5):66-72.(in Chinese))

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 在线发布日期: 2019-10-30