Cause analysis of face cracking of a CFRD during construction period in cold regions
CSTR:
Author:
Affiliation:

Clc Number:

TV641.4

Fund Project:

  • Article
  • |
  • Figures
  • |
  • Metrics
  • |
  • Reference
  • |
  • Related
  • |
  • Cited by
  • |
  • Materials
  • |
  • Comments
    Abstract:

    In view of the face cracking of a CFRD during construction in cold regions, the structural deformation, temperature variation, hydration temperature rise and its own shrinkage were analyzed with an actual project based on prototype monitoring. It is found that the highest value of the hydration temperature rise and the maximum temperature difference in the later cooling is the main factor affecting the temperature difference of cumulative cooling. When the temperature difference of the cumulative cooling is larger, the temperature stress may exceed the tensile strength of the panel concrete, causing panel cracking. Suggestions for avoiding temperature cracks were put forward for construction projects with larger annual temperature difference and higher hydration temperature during the concrete pouring period, such as optimizing the concrete mix ratio, optimizing the construction process and improving concrete crack resistance.

    Reference
    Related
    Cited by
Get Citation

何鲜峰,汪自力,何启.寒冷地区面板堆石坝施工期面板开裂原因[J].水利水电科技进展,2019,39(3):68-74.(HE Xianfeng, WANG Zili, HE Qi. Cause analysis of face cracking of a CFRD during construction period in cold regions[J]. Advances in Science and Technology of Water Resources,2019,39(3):68-74.(in Chinese))

Copy
Related Videos

Article Metrics
  • Abstract:
  • PDF:
  • HTML:
  • Cited by:
History
  • Received:
  • Revised:
  • Adopted:
  • Online: May 27,2019
  • Published:
Article QR Code