基于调度线预调水量优化的南水北调东线工程联合优化调度
作者:
作者单位:

(1.水利部水利水电规划设计总院;2.水利部水利规划与战略研究中心;3.江苏航运职业技术学院;4.中水东北勘测设计研究有限责任公司;5.中国南水北调集团东线有限公司;6.天津大学建筑工程学院;7.河海大学水文水资源学院 )

作者简介:

郭旭宁(1983—),男,正高级工程师,博士,主要从事水网规划与调度研究。E-mail:guoxuning@giwp.org.cn

通讯作者:

中图分类号:

基金项目:

国家重点研发计划项目(2022YFC3202300);水利部水利水电规划设计总院“揭榜挂帅”项目(水总人【2025】15号);中国南水北调集团有限公司科研项目(DXZ-2023-081-ZD-ZX)


Joint optimal dispatching of South-to-North Water Diversion Eastern Route Project based on dispatch lines and preallocated water volume optimization
Author:
Affiliation:

(1.MWR General Institute of Water Resources and Hydropower Planning and Design(GWP);2.MWR Center for Water Resources Planning and Strategic Research;3.Jiangsu Shipping College;4.China Water Resources Northeastern Investigation, Design & Research Co., Ltd.;5.China South-to-North Water Diversiong Eastern Route Corporation Limited;6.School of Civil Engineering, Tianjin University;7.College of Hydrology and Water Resources,Hohai University)

Fund Project:

undefined

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 文章评论
    摘要:

    为适应南水北调东线工程水源区径流演变特征,充分发挥多水源之间的水库库容补偿作用,建立了南水北调东线工程水资源联合优化调度模型,以调度线优化、预调水量优化和调度线预调水量协同优化3种模式进行模型求解,得到了考虑近年径流演变规律的优化调度线和各优化模式的调度结果,并基于原调度线模拟结果进行多模式对比分析。结果表明:相较原调度线模拟结果,优化调度线能够在不损害原受水片区利益的前提下有效降低南水北调东线工程受水片区缺水量;预调水量优化模式在略微增加原受水片区缺水量的情况下,可满足南水北调东线工程受水片区所有用水需求;调度线预调水量协同优化模式相较于仅优化调度线,进一步降低了南水北调东线工程受水片区缺水量,更为高效合理。

    Abstract:

    To adapt to runoff evolution law in water source areas of South-to-North Water Diversion Eastern Route Project and give full play to hydrological reservoir capacity compensation effect of multiple water sources, a joint optimal dispatching model for project is established. The model is solved under three modes:dispatching line optimization, pre-allocated water volume optimization, and joint optimization of dispatching line and pre-allocated water volume. The optimized dispatching lines considering runoff evolution law in recent years and dispatching results of each optimization mode are obtained. A comparative analysis of different modes is conducted based on simulation results of original dispatching lines. The results show that compared with simulation results of original dispatching lines, optimized dispatching lines can effectively reduce water deficit in water receiving areas without impairing interests of original water receiving areas. Pre-allocated water volume optimization slightly increases water deficit of original water receiving areas, yet fully meets all water demands in eastern route area. Compared with single dispatching line optimization, the joint optimization of dispatching line and pre-allocated water volume further cuts down water deficit in eastern route area, proving more efficient and reasonable.

    参考文献
    相似文献
    引证文献
引用本文

郭旭宁,李云玲,卢庆文,等.基于调度线预调水量优化的南水北调东线工程联合优化调度[J].水资源保护,2026,42(3):191-197, 240.(Guo Xuning, Li Yunling, Lu Qingwen, et al. Joint optimal dispatching of South-to-North Water Diversion Eastern Route Project based on dispatch lines and preallocated water volume optimization[J]. Water Resources Protection,2026,42(3):191-197, 240.(in Chinese))

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:
  • 最后修改日期:
  • 录用日期:
  • 在线发布日期: 2026-06-16
  • 出版日期: